Bass Gold
3 February, 2024
The construction of the factory at the Ushshoky mine is nearing completion
The construction of the gold beneficiation plant at the Ushshoky deposit by "BASS Gold" is nearing completion, as reported by the PR department of BASS Holding. As part of the construction work, crushing and grinding equipment for the preliminary preparation of ore mass from the mine has been put into operation. The installation of equipment for the hydrometallurgical plant for ore leaching has also been carried out, along with the procurement of additional machinery to increase extraction volumes. All activities within the construction of the new gold extraction plant and the modernization of the mine have already resulted in a 122% increase in monthly productivity. As a reminder, according to the Holding's strategy, the Ushshoky deposit will be involved in the production of the final product in the form of Dore alloy.